Page 9 of 9
Seven-Year Timeline
A timeline is proposed for the projects within this Tactical Plan.
Assumptions:
- Preparation for each project will take about 3 months (1 quarter). Preparation includes identifying funding, resourcing and project set-up.
- 3-6 months is the typical time-frame for the actual work on each project.
|
Yr 1 |
Yr 2 |
Yr 3 |
Yr 4 |
Y4 5 |
Yr 6 |
Yr 7 |
| E3-FA1: Integration of Engineering and Project Controls with Procurement |
|
|
|
|
|
|
|
| E3-FA1-P1 |
Definition of Work Processes and Systems for Engineering, Project Control, Materials Handling and Labor Tracking |
Q3-Q4 |
Q1-Q2 |
|
|
|
|
|
| E3-FA1-P2 |
Information protocols for Engineering, Project Control, Materials Handling and Labor Tracking |
|
Q3-Q4 |
Q1-Q2 |
|
|
|
|
| E3-FA1-P3 |
Information protocols for Procurement Process Financial Interoperability |
|
|
|
Q1-Q4 |
|
|
|
| E3-FA1-P4 |
Intelligent Project Analyst |
|
|
|
|
Q1-Q4 |
|
|
| E3-FA2: Supply Chain Information Access and Standards |
|
|
|
|
|
|
|
| E3-FA2-P1 |
Automating Equipment Information Exchange (AEX) |
Q1-Q4 |
Q1-Q4 |
|
|
|
|
|
| E3-FA2-P2 |
Protocols for Exchanging Fabrication Progress Information |
|
Q1-Q4 |
|
|
|
|
|
| E3-FA2-P3 |
Standardized Supplier Documentation Requirements |
Q3-Q4 |
Q1-Q4 |
|
|
|
|
|
| E3-FA2-P4 |
Standardized On-line Capabilities for Supplier and Procurement Community |
Q1-Q4 |
Q1-Q4 |
Q1-Q4 |
|
|
|
|
| E3-FA2-P5 |
Automated Supplier Certification Protocols |
|
|
|
|
|
Q1-Q4 |
|
| E3-FA2-P6 |
Customs and Standards Knowledgebase |
|
|
|
|
|
Q1-Q4 |
|
| E3-FA3: Integration of Procurement with Intelligent Job Site |
|
|
|
|
|
|
|
| E3-FA3-P1 |
Real-time material logistics: tracking and trafficking |
|
|
|
Q1-Q4 |
|
|
|
| E3-FA3-P2 |
Materials security and regulatory compliance streamlining |
|
|
|
|
Q1-Q4 |
|
|
| E3-FA3-P3 |
Optimized job site materials management |
|
Q1-Q4 |
Q1-Q4 |
|
|
|
|
| E3-FA3-P4 |
Identification and Management of Scarce and Long Lead Items |
Q3-Q4 |
|
|
|
|
|
|
| E3-FA4: Evaluation of Supply Chain Structures |
|
|
|
|
|
|
|
| E3-FA4-P1 |
Supply-chain Performance Metrics |
|
|
|
Q1-Q4 |
|
|
|
| E3-FA4-P2 |
Models for Risk/Value Management of Procurement Items |
|
|
|
Q3-Q4 |
|
|
|
| E3-FA4-P3 |
Dynamic Mapping and Simulation of Supply Chains |
|
|
|
|
|
|
Q1-Q4 |
|
|
Last Updated on Friday, 05 June 2009 10:42 |